³í¹®¸í |
ÆÛÁöÃ߷бâ¹Ý ¿øÀü Â÷Æó ÄÜÅ©¸®Æ® ±¸Á¶¹° ÇØÃ¼°øÁ¤ ¸®½ºÅ© Æò°¡ - ±¸Á¶Àû¡¤ÀÛ¾÷ ¸®½ºÅ© Áß½ÉÀ¸·Î - / Risk Assessment on Decommissioning Process of Nuclear Power Plant Bio-shield Structure based on Fuzzy Inference - focusing on structural damage / work process risks - / session 2 : ³»±¸¼º |
¼ö·Ï»çÇ× |
Çѱ¹°Ç¼³¼øÈ¯ÀÚ¿øÇÐȸ Çмú¹ßÇ¥ ³í¹®Áý, Vol.18 n.2 (2018-11) |
ÆäÀÌÁö |
½ÃÀÛÆäÀÌÁö(15) ÃÑÆäÀÌÁö(4) |
¿ä¾à1 |
¿øÀڷ½ü³ ÇØÃ¼»ç¾÷ÀÇ ¸®½ºÅ© ¾ÈÀü¼º Æò°¡ °ü·Ã ¿¬±¸°¡ °ÅÀÇ ¾øÀ¸¸ç, ºÐ¼®À» À§ÇÑ °¡¿ë µ¥ÀÌÅ͵µ Àü¹«ÇÑ »óÅÂÀÌ´Ù. ¼±Çà ¿¬±¸´Â ´ëºÎºÐ ¹æ»ç¼± ¸®½ºÅ©¿¡ ÃÊÁ¡ÀÌ ¸ÂÃß¾îÁ® ÀÖ¾î ±¸Á¶Àû/ÀÛ¾÷ °üÁ¡¿¡¼ÀÇ À§Çù¿äÀÎÀ» °í·ÁÇÑ ¸®½ºÅ©¿¡ ´ëÇÑ ¿¬±¸°¡ ÇÊ¿äÇÏ´Ù. º» ¿¬±¸¿¡¼´Â ±âÁ¸ÀÇ °áÁ¤·ÐÀû ¸®½ºÅ© Æò°¡¹æ¹ýÀÇ ÇѰèÁ¡À» ÁöÀûÇÏ°í ±× ´ë¾ÈÀ¸·Î ÀÛ¾÷ÇÁ·Î¼¼½ºº° ¸®½ºÅ©ÀÇ Á¤·®È ¹× ´ÙÂ÷¿øÀû Á¢±ÙÀ» ÅëÇÑ ´ë¾ÈºÐ¼® ¹× ºñ±³°¡ °¡´ÉÇÑ ¸ðµ¨À» Á¦½ÃÇϰí Case Study¸¦ ¼öÇàÇÑ´Ù. |
¿ä¾à2 |
Few studies have been conducted on risk safety assessment of decommissioning projects of nuclear facilities, and there is no available data for analysis. Most of the previous researches focus on radiological risks, so it is necessary to study the risks considering the threats factor from the structural / work point of view. In this paper, we point out the limitations of existing deterministic risk assessment methods and propose an alternative analysis and comparison model through quantitative and multidimensional approach to each work process and conduct a case study. |