| 논문명 |
TACT 공정기법의 작업 유형 분류를 통한 진도관리 개선 방안에 관한 연구 / A Study on Improvement of Progress Control through Classification of Work Types of TACT Scheduling Method |
| 저자명 |
이승훈 (Lee Seung-Hoon) ; 최청균(Choi Chung-Gyun) ; 김주형 (Kim Ju-Hyung) ; 김재준 (Kim Jae-Jun) |
| 수록사항 |
대한건축학회논문집 구조계, v.27 n.1 (2011-01) |
| 주제어 |
TACT ; 작업량 ; 마감공사 ; 작업성취율 ; 진도관리 ; TACT ; Workload ; Finish Work ; PPC ; Progress Control |
| 요약2 |
In apartments, cost of finishing work comprises a large part of gross construction costs, and also subcontractors put in apartment finishing work outnumber those put for its structure construction by far. As various processes take place at the same time, period of construction widely differs depending on management ability of the constructors. But in most cases, a difference between plan and outcome is caused by incorrect process plan and inefficiency of process management during finishing work. For this reason, field administrators should make sure of precise process by measuring the workload required for finishing work and reflect it to the actual construction. Finishing work in apartments means follow-up works after structural construction and with a number of divided process, is composed of very various and complicated elements. TACT scheduling method, which enhances work efficiency and maintains smooth flow of work by application to the repeated process like finishing work, is a reasonable progress control technique that may reduce the probability of construction delay or rise of construction costs. This study classifies minimum work types applicable to TACT method to maintain efficient flow of work and reflects actual accomplishment ratio to progress control. And eventually it aims to provide construction participators with information needed to establish process plan of finishing work. |